Campus & Community Information
Capital Request
(Fiscal Year 08)
Building Abbreviations
& Numbers (pdf)
Design & Construction
Professionals
Turner Hall
© Google map
Architects/Engineers: Clark Dietz Engineers/ BLDD Architects
General Contractor: Bishop Brothers Construction Co.
ISU Administrator Contact: Rick Kentzler/ Christine Tsui
ISU Project Manager: Bill Waters
Project Status: Construction
Fund Source: CDB
Project Budget: $23,300,000
The Life Safety Improvement Project for Stevenson and Turner Halls will begin during the summer of 2007. The project will consist of three phases and the buildings will be partially occupied during construction.
The first phase includes upgrades to the third and fourth floors of Stevenson Hall. Beginning of summer 2008, the second phase will upgrade the first floor, second floor, and the basement. The third and final phase will be the upgrade to Turner Hall beginning of summer 2009.
The primary intent of this project is to correct problems with the life safety systems and upgrade the mechanical and electrical systems for these two classroom and office buildings.
The project will also bring both buildings into compliance with the Americans with Disabilities Act (ADA) requirements and infrastructure deficiencies.
Update:
Stevenson and Turner - Relocation Project:
The occupant and classroom relocation progress is underway, to be divided into three phases. The moving contractor is Federal Johnson Moving Storage.
Phase 1 Moves
The move for Phase 1 was completed May 14-29, 2007. This phase included moving occupants, offices, classrooms, furniture, computers, monitors, and boxes temporarily relocated from the 3rd and 4th floor of Stevenson to Williams Hall, Turner Hall, the lower level of College of Business Building, and Warehouse Road during construction.
Phase 2 Moves
These are activities associated with the Stevenson Hall move during the summer:
June 2009 - Move back into Basement, 1st, and 2nd floors of Stevenson Hall.
Phase 3 Moves
July 2009 - Move out of Turner Hall.
December 2009 - Move back into South Wing of Turner Hall.
July 2010 - Move all occupants back into Turner Hall.