Stevenson/ Turner - Life Safety Improvement Project

Stevernson Hall construction Turner Hall

Architects/Engineers: Clark Dietz Engineers/ BLDD Architects
General Contractor: Bishop Brothers Construction Co.
ISU Administrator Contact: Rick Kentzler/ Christine Tsui
ISU Project Manager: Bill Waters
Project Status: Construction
Fund Source: CDB
Project Budget: $23,300,000

Description

The Life Safety Improvement Project for Stevenson and Turner Halls will begin during the summer of 2007. The project will consist of three phases and the buildings will be partially occupied during construction.

The first phase includes upgrades to the third and fourth floors of Stevenson Hall. Beginning of summer 2008, the second phase will upgrade the first floor, second floor, and the basement. The third and final phase will be the upgrade to Turner Hall beginning of summer 2009.

The primary intent of this project is to correct problems with the life safety systems and upgrade the mechanical and electrical systems for these two classroom and office buildings.

The project will also bring both buildings into compliance with the Americans with Disabilities Act (ADA) requirements and infrastructure deficiencies.

Update:

  • The general contractor completed the installation of the construction fence on the east and south sides of Stevenson Hall on June 15, 2007. As a result, the building now has two public entrances: one located on the northwest corner, and the other located on the west side of the building. See attached pedestrian map for further location information. Stevenson Hall Pedestrian route
  • construction fence and construction photos
  • The asbestos contractor has completed the asbestos abatement on both the 3rd and 4th floors. In addition the contractor has completed 90 percent of the abatement work associated with the basement of Stevenson.
  • The plumbing contractor has removed and replaced water mains and branch lines above the ceiling on the 3rd and 4th floors and basement.
  • The electrical contractor has completed the cable tray and communication cable on the 4th floor. The contractor continues to install cable tray, communication cable, lighting, and fire alarm circuits on the 3rd floor. 
  • The mechanical contractor is installing piping to the reheats on the 3rd floor as well as ductwork.
  • The general contractor is building soffits and fire walls on the 3rd and 4th floors as well as installing ceiling grid in the offices and classrooms on the 4th floor. (See photo below.) 
  • Anticipated completion of phase one is July 31, 2008. Building Services of Facilities Management will clean the building before it is reoccupied.       Stevenson - interior work        

Stevenson and Turner - Relocation Project:

The occupant and classroom relocation progress is underway, to be divided into three phases. The moving contractor is Federal Johnson Moving Storage.

Phase 1 Moves

The move for Phase 1 was completed May 14-29, 2007. This phase included moving occupants, offices, classrooms, furniture, computers, monitors, and boxes temporarily relocated from the 3rd and 4th floor of Stevenson to Williams Hall, Turner Hall, the lower level of College of Business Building, and Warehouse Road during construction.

Phase 2 Moves

These are activities associated with the Stevenson Hall move during the summer:

  • May 12-23 Interim moves within Williams Hall
  • May 12-23 Stevenson basement, 1st, and 2nd floors to Williams
  • Aug 4-15  Williams Hall to Stevenson 3rd and 4th floor
  • Aug 4-15   Interim moves within Williams Hall

June 2009 - Move back into Basement, 1st, and 2nd floors of Stevenson Hall.

Phase 3 Moves

July 2009 - Move out of Turner Hall.

December 2009 - Move back into South Wing of Turner Hall.

July 2010 - Move all occupants back into Turner Hall.